Goods Yard
Opportunity
Capital & Centric is on the hunt for creative businesses and the best independent bars, eateries and stores to accompany the already impressive list of tenants at Goods Yard. There are still a mix of spaces available across the development, including the locally listed Vaults Warehouse, the Victorian Signal Box and a 3,000sqft unit at the ground floor of the residential new-build, with direct links to the train station.
Each unit is packed with character, from original brickwork to exposed concrete soffits.
There’s also loads of space to spill out on to the lush public square and canal side jetty. Goods Yard will be a major destination for residents, locals and visitors. This is your chance to be one of the first to set the scene for the new era of Stoke-on-Trent.
Programme
• Planning Approval – March 2022
• Enabling Works – March 2022 to August 2022
• Main Works – September 2022 to April 2025
Development mix
- Goods Yard Living: 174 design led apartments for rent, with a mix of 1,2 and 3-bed homes with ground floor resident facilities and amenities space
- Signal box: a café-bar in the currently derelict rail signal box
- Vaults Warehouse: Restoration of brick vaulted, below ground warehouse to create work and leisure space
- Canalside Jetty: Opening up the water’s edge to the public
- The Pavilion: 5,000 sq.ft. in a double height space for workspace and/or leisure use
- The Goods Yard square: a bustling public square with gardens, space for pop up events, with pedestrian and cycle links to the surrounding area
- Hotel: 150 bed hotel (to be delivered as part of phase 2)
Interested in this project?
Get in touch below to find out more.